A slab cast today is not at full strength tomorrow. Curing is what lets concrete reach its designed strength.
Why curing matters
Concrete gains strength through a chemical reaction that needs water. If the surface dries out too soon, the top layer becomes weak, develops shrinkage cracks and loses durability. Properly cured concrete can be up to 40% stronger than poorly cured concrete.
How long to cure
As per IS 456, ordinary Portland cement concrete should be cured for at least 7 days, and for 14 days where possible. Slabs and columns exposed to weather benefit from the longer period. The first 24 to 48 hours are the most critical.
Common methods
Ponding water on flat slabs is the simplest and most effective method. Wet hessian or gunny bags, sprinkling, and covering with plastic sheets all help retain moisture. Membrane-forming curing compounds are useful where water is scarce.
Mistakes to avoid
Do not let the slab dry in the sun right after casting. Do not stop curing after one or two days. And never load a slab heavily before it has gained sufficient early strength.